How to Conduct a Factory Acceptance Test for Used Equipment

A factory acceptance test for used equipment should be planned before shipment and cover records, physical condition, safety features and operation against agreed acceptance criteria. It is usually carried out before the machine is disassembled or packed, giving the buyer a chance to identify issues before transport. A FAT isn’t legally required, but it is often included in the purchase contract as a condition of shipment or payment release.

A run test alone cannot show whether the equipment is complete, whether its condition matches the available records or whether important safety and functional checks have been missed. A clear plan helps the buyer and supplier agree on what to inspect, how to assess each test and what must be resolved before dispatch.

This guide explains how to set acceptance criteria, organise the test, review documentation and assess mechanical, electrical, safety and functional performance. It also covers how to record defects and decide whether the equipment is ready to ship or needs further work.

Key Takeaways

  • Set clear acceptance criteria before testing so the buyer and supplier share the same basis for assessing the equipment.
  • Separate pre-shipment testing from site acceptance: each checks performance in a different operating context.
  • Review equipment records alongside its physical condition to identify gaps that could affect operation or maintenance.
  • Build mechanical, electrical, safety and functional checks around the equipment’s design and intended use.
  • Document test results and outstanding issues, then use them to determine whether the equipment is ready for shipment.

What is Factory Acceptance Testing?

Before shipment, a factory acceptance test for used equipment checks whether the machine meets agreed requirements through document review, physical inspection and functional testing. In Australia, the cost depends on equipment type, test scope, preparation and whether testing is remote or on site. The price is provided after a quote request.

  1. Compare FAT with Site Acceptance Testing

    Keep pre-shipment acceptance testing separate from checks performed after installation. A FAT examines the equipment before it leaves the supplier, usually at the supplier’s facility. A site acceptance test, or SAT, checks operation after installation under actual site conditions. For example, a FAT can assess a pump using factory utilities, while a SAT checks its connection to the plant’s piping and supply.

    Use the FAT to find equipment-level issues and the SAT to assess integration. A FAT may take hours to several days, depending on complexity; SAT duration depends on the integration scope.

  2. Define Simulated Operating Conditions

    Specify the operating conditions the supplier must reproduce and the evidence that will demonstrate acceptable function. Use available test fixtures, factory power or air to operate controls and simulate the intended process. For a bottle filler, define the operating sequence and observe whether its functions respond as expected.

    Record the limits of each simulation. Factory testing cannot fully reproduce actual site utilities, connected equipment or production materials, so simulated results do not replace commissioning after installation.

  3. Verify Used Equipment Performance and Condition

    Compare the machine’s physical condition with its available records and the agreed test criteria. Match its identification and major components to the documentation, then inspect for visible damage, wear, missing parts or modifications. During operation, record observations against defined criteria rather than relying on a general statement that the machine runs.

    For rotating equipment, include relevant checks such as motor rotation, vibration and coupling alignment. Link each result to the component tested, the test conditions and any observed defect.

  4. Agree how to conduct testing if the equipment is already installed or no longer at the factory. A FAT can take place at the customer’s site when necessary, but equipment that is already installed is better assessed through testing that reflects its actual connections and operating context. Remote testing lets stakeholders observe procedures and review records without attending in person.

    For remote testing, agree how the supplier will show the machine, test readings and results. Identify which inspections require direct physical access, since a camera view cannot establish every aspect of the equipment’s condition.

  5. Set out the test procedure, acceptance criteria, responsibilities and shipment conditions in the purchase contract. A FAT isn’t legally required, but contracts often make it a condition of shipment or payment release. Schedule the test after final assembly and internal commissioning, but before disassembly, crating or packing.

    If a test fails, record the result, defect and required corrective action. Agree whether the supplier must rectify the issue and repeat the test before shipment. FAT findings are limited to the tests performed, the simulated conditions and the equipment’s state on the test day. They cannot establish how the machine will perform in every future production scenario.

Documentation and operations and maintenance records

Organise records around the equipment’s identity, history and agreed test scope. A well-ordered file lets the buyer compare the machine’s actual configuration with its drawings and recorded test results.

  1. Plan FAT Documentation

    Assemble the test file before the FAT, using customer specifications, drawings, data sheets, an inspection test plan, applicable codes, procedures and required calibration certificates. Arrange the documents by test sequence so the buyer and supplier can find the relevant acceptance criterion during each check.

    Identify who records results, who reviews them and who signs each test record. Include space for failed tests, corrective actions and retest outcomes. Avoid leaving acceptance decisions to informal verbal agreement.

  2. Gather Engineering and Materials Records

    Match the equipment’s identification details to its general arrangement, electrical drawings and piping and instrumentation diagrams. Compare the physical assembly with the drawings, then record differences such as changed connections, substituted components or removed instruments. This helps distinguish an approved configuration change from an unexplained discrepancy.

    Gather available materials and component records relevant to the machine’s design and operation. For example, file component data sheets with the relevant equipment documents rather than separately without an identifier. Use revision details to verify that reviewers are assessing the correct drawings.

  3. Record FAT Results

    For each test, record what was tested, the method, the result and whether it met the stated acceptance criterion. Include raw test data where required, along with the test instrument’s identification and calibration status. A signed record should identify the reviewer and show whether the result passed, failed or needs follow-up.

    Record defects as specific findings, not broad comments. Identify the affected component and observed issue, then document corrective work and retest results. Keep failed and repeated tests in the record so the final handover reflects the complete test history.

  4. Review operation and maintenance records for evidence of previous servicing, repairs and component changes. Match each entry to the equipment or component it describes. A maintenance note that says only “pump serviced” is difficult to verify; an entry identifying the pump and work performed is more useful for future maintenance planning.

    Compare listed maintenance tasks with the equipment manuals and available service documents. Record gaps or inconsistencies for resolution, and clearly distinguish historical records from work completed during the current FAT.

  5. Prepare a handover package containing the FAT results, component manuals and as-built drawings. Check that the documents describe the equipment as tested, not an earlier configuration. Include the final test records and any resolved corrective actions, so the receiving team can understand the equipment’s documented condition and operation.

    Before shipment, check that the file is complete, legible and correctly identified. Store the signed records with the equipment documentation, and provide the operations and maintenance team with relevant manuals and drawings for installation and ongoing use.

Mechanical, electrical, safety and functional checks

A used equipment FAT checklist should cover drawings, physical condition, electrical connections, safety features and operation. Set each check against the equipment’s specifications and record whether the result meets the expected function.

  1. Compare Equipment with Technical Drawings

    Compare the assembled machine with its technical drawings and specified design. Check dimensions, component locations, connections and modifications against the current drawings, and note discrepancies for review. Confirm that inputs and outputs connect as shown and that the arrangement follows the manufacturer’s specifications. Do not accept an undocumented change as a match simply because the equipment operates.

  2. Inspect Visual and Mechanical Condition

    Inspect the equipment’s physical condition before operation, then examine moving parts during testing. Look for visible damage, loose or missing components, sharp edges, pinch points and signs of leakage. For rotating equipment, check motor rotation, vibration and shaft or coupling alignment. Record observations against the checklist and expected operating behaviour.

  3. Check electrical and control components against the drawings and specified hardware and software versions. Inspect wiring and connections, then test relevant controls and functions. Confirm that control responses match the documented sequence, and note inconsistent indications or unexpected stopping behaviour. Include equipment-specific checks for switches and built-in safety components.

    For machinery with control software, verify that the installed version is compatible with the specified configuration. Test inputs and outputs according to the drawings, and document the response to each relevant command. A control test should show what was activated and how the machine responded, rather than simply recording that it passed.

  4. Review guarding, limit switches and emergency stops before functional testing. Confirm that nameplates are visible, emergency stop buttons are accessible and safety switches are installed. Trigger relevant safety shutdowns during the test and check that the machine reaches a safe state. Identify hazards in the test area before acceptance testing begins.

    Record any safety concern as a specific finding, including its location and observed effect. An accessible emergency stop does not prove that the full shutdown function works; test the response and record the result.

  5. Perform functional tests using the agreed procedure, then record results against each acceptance criterion. A machine may be dry-cycled for at least 24 hours during factory testing. Use the test period to observe operating sequence, control response and recurring faults, rather than relying on a brief start-up alone.

    Keep the checklist tied to the machine’s actual configuration and intended use. Separate visual findings, mechanical observations, electrical checks and functional results so reviewers can identify the source of any failure and assess whether corrective work is needed.

How to Conduct a Factory Acceptance Test for Used Equipment

FAT versus commissioning and pre-shipment inspection

Keep the FAT, commissioning and pre-shipment inspection distinct by objective and timing. For an Australian FAT, identify the applicable state or territory WHS requirements and any equipment-specific standards in the contract. Do not assume one standard covers every used machine.

  1. Define what the FAT is intended to establish before testing begins. It checks whether the equipment meets the agreed requirements at the supplier’s facility before shipment. Commissioning follows installation and focuses on preparing the machine for operation in its actual setting. A pre-shipment inspection focuses on the equipment’s condition and readiness for dispatch.

    Keep the records distinct. A successful FAT does not prove that the machine has been installed correctly, and a visual inspection alone does not demonstrate operating performance.

  2. Identify hazards in the test area before anyone inspects or operates the machine. Consider equipment movement, stored energy, exposed drive components and access routes. For example, a mixer with an accessible shaft needs a controlled test area and a clear procedure for stopping operation.

    Plan isolation and lockout/tagout steps before maintenance or close inspection. Identify the relevant energy sources and isolation points, and make sure the test team understands when the machine must remain stopped.

  3. Inspect physical condition by following a consistent route around the equipment. Examine the frame, guards, access doors, fasteners, visible pipework and electrical enclosures. Record damage, corrosion, leakage or missing guards by location, then compare each finding with the agreed scope and available drawings.

    For an industrial machine with moving parts, check that guards are present and securely fitted before functional testing. Do not remove a guard to improve visibility while the machine is operating; arrange a safe inspection while it is stopped.

  4. Complete a final inspection after testing and before the equipment is moved or packed. Check for new damage, loose components, removed test fittings and unresolved punch-list items. Compare the machine’s final condition with the inspection record to ensure testing has not introduced an overlooked defect.

    Document each outstanding item, its location and the agreed resolution. Clear the FAT punch list before the equipment is moved or shipped, and retain records of corrective work and any required retesting.

  5. Use commissioning to assess site-specific operation after installation. Confirm how the equipment interacts with actual utilities, connected machinery and production materials, since these conditions differ from factory test arrangements. Record commissioning findings separately from the FAT result.

    For machinery relocation, coordinate the handover between pre-shipment checks and site commissioning. This helps distinguish a transport or installation issue from a fault observed during the original factory acceptance test.

Apply the WHS requirements of the relevant state or territory and the equipment-specific standards agreed in the contract. No single standard is assumed to cover every used machine. The FAT plan should also address test-area hazards and set out isolation and lockout/tagout steps before maintenance or close inspection.

Developing a test plan and acceptance criteria

Build the test plan around the purchase requirements, the equipment’s current configuration and the evidence needed for acceptance. Clear criteria make each test result actionable, rather than leaving the buyer and supplier to interpret “working” differently.

  1. Start the plan during the order bid phase, then submit it with the request for quote. Include customer specifications, engineering drawings, data sheets, applicable codes, test procedures and required calibration certificates. For used machinery, identify the configuration to be tested, including recorded modifications, so the supplier can prepare the correct test setup.

    Assign responsibility for each task: who conducts the test, who records readings and who approves results. Specify required witnesses and deliverables in the contract, alongside any relationship between acceptance, shipment and payment.

  2. Translate every purchase requirement into a measurable acceptance criterion. State the test method, expected result and evidence that will demonstrate compliance. For example, a bottle filler test could identify the operating sequence to demonstrate and the recorded output that will count as a pass.

    Avoid criteria such as “runs satisfactorily” without a defined observation. Use a specific, observable response, measurement or documented inspection result, and state how deviations will be recorded and assessed.

  3. Arrange tests in a logical sequence, with a review and sign-off point before the next test begins. Start with document and configuration checks, then proceed to inspections and functional tests. This staged approach gives engineering reviewers time to resolve discrepancies before they affect later results.

    Check that test instruments are within their required calibration dates before taking readings. Record the instrument identification alongside each result, so another reviewer can understand how the measurement was obtained.

  4. Define the test conditions, including materials and utilities, before the supplier conducts the FAT. Where practical, use materials intended for actual production, as they can reveal behaviour that an empty or simulated run may not show. Document any difference between the test setup and intended operating conditions.

    Separate factory criteria from site acceptance test criteria. The FAT assesses what can be demonstrated before dispatch, while site acceptance addresses integration with site utilities, connected systems and production conditions.

  5. Set rules for recording failures, corrective actions and retests. Each failed criterion should identify the result, affected component and required resolution. State who reviews corrective evidence and signs the final disposition before shipment.

    Keep the plan controlled as manufacturing information and equipment configuration change. ISO 9001 provides a quality management framework for supplier testing and documentation practices, but it doesn’t prescribe a specific FAT procedure. Tailor the test sequence to the machine and agreed requirements.

For buyers assessing bottle filling equipment, explore bottle fillers alongside the specifications your test plan needs to address.

F.A. Maker: Used Stainless Steel Tanks

F.A. Maker supplies used stainless steel tanks for Australian industrial processing. After defining your acceptance criteria, use them to assess whether a tank’s documented condition and function suit your process.

F.A. Maker also offers centrifuges and separators, industrial mixers and blenders, and pumps and valves. These equipment categories can support different stages of a processing line, so consider the machine’s role, connection requirements and intended operating conditions when planning your purchase evaluation.

For a used equipment decision, compare the equipment’s specifications and available records with the needs in your test plan. Visit famaker.com.au to explore the equipment range or contact F.A. Maker with your requirements.

Make the next equipment decision with clear criteria

Use your FAT findings as a practical decision record, not just a pass-or-fail document. The observations and criteria you establish can guide discussions about equipment suitability, required corrective work and checks after installation. For a factory acceptance test for used equipment, keep the purchase requirements tied to the machine’s intended role and the evidence gathered during evaluation.

F.A. Maker offers used stainless steel tanks, centrifuges and separators, and industrial mixers and blenders. These categories serve different process requirements, so define the equipment’s intended duty and key specifications before comparing options. A well-defined requirement keeps the next step focused on operational fit rather than a general search for machinery.

If you’re assessing used process equipment for a project, contact F.A. Maker about used equipment. Bring your process requirements and evaluation priorities into the discussion, then move forward with a clearer basis for your decision.

Frequently Asked Questions

What happens if you skip it or rush it?

Skipping or rushing a FAT can leave faults undiscovered until the equipment reaches the buyer’s facility. A control fault might appear only during a particular operating sequence, while transport can make later inspection and correction more difficult. A limited test also gives the buyer less evidence for resolving disagreements about condition or performance. Match test time to equipment complexity and document any checks that could not be completed.

Who should be involved in a FAT?

Include people who can assess the equipment technically and those who will operate or maintain it. The buyer’s project manager can track requirements, an engineer can review technical results, and an operator can assess practical controls and access. The supplier’s technical team should explain the test setup and respond to findings. For specialised machinery, an independent inspector can witness relevant checks on the buyer’s behalf.

What is a factory acceptance test (FAT) for used equipment?

A factory acceptance test for used equipment is a pre-shipment examination of its records, physical condition and operation against agreed purchase requirements. It helps the buyer assess the specific machine being purchased, rather than relying only on a description or previous operating history. The test can combine inspection, document review and functional checks. Its scope should reflect the machine’s current configuration and intended duty.

Who should witness and sign off a used equipment FAT?

The buyer’s designated technical representative should witness the checks they need to assess, with the supplier’s representative present to explain the equipment and record outcomes. The contract or test plan should name who can approve results and accept outstanding actions. Sign-off should identify the tested machine and the records reviewed. A witness confirms what they observed; that alone does not mean every requirement has passed.

What documents and test records should sellers provide for used equipment?

Request records that identify the specific machine, such as available manuals, drawings, service history, component information and current test results. Each record should be traceable to the equipment’s identification details and show its revision or date where applicable. For example, a maintenance entry should identify the component and work performed. Ask for readings and outcomes from tests, including recorded failures and retests, not just a pass statement.

What is the difference between a factory acceptance test and a site acceptance test for used equipment?

A FAT assesses the machine before dispatch, while a site acceptance test checks it after installation in its operating environment. The site test can reveal issues that factory testing cannot, such as a mismatch with connected equipment, site utilities or production materials. For example, a machine may operate on a factory test setup but need further adjustment once connected to the buyer’s process line.

What contract terms should specify FAT criteria, defects, repairs and acceptance for used equipment?

Set out the test scope, measurable pass criteria, responsible parties, required records and who can approve acceptance. Specify how defects will be logged, who determines corrective work, how retesting will be recorded and how unresolved items affect shipment or payment. Identify tests excluded from the FAT and distinguish them from later site checks. Clear wording gives both parties a shared basis for resolving test findings.